Cheyenne Data Center Power: Utility Builds Gas Plant for Google

Black Hills builds a 564 MW utility-owned gas plant for Google's Cheyenne data center, with a 2.1 GW microgrid and contracts to 2048.

Audio version: AI-generated from this text by bytevyte, read by a synthetic voice.

A 2.7 GW resource mix, including a 564 MW gas plant owned by the utility, will power Google's planned Cheyenne data center, according to Black Hills Energy. The arrangement, announced on October 6 and running under contracts to 2048, pairs utility-built generation with about 2.1 GW of third-party plants that the utility coordinates through a privately managed microgrid for a fee. A second hyperscaler, Microsoft, has also filed grid agreements in Wyoming, which puts the question of who pays for the AI power build-out in southeast Wyoming on the table.

The utility is Cheyenne Light, Fuel and Power Co., whose parent is now Bright Horizon Energy Corp., which was renamed from Black Hills Corp. following its combination with NorthWestern Energy Group. The facility Google plans to use should start operating in late 2027 and ramp up to its full anticipated demand by the close of 2030.

Who Carries the Cost

Google has stated in its own announcement that it will pay for 100% of the power its Wyoming campus uses and will cover the infrastructure needs directly driven by its growth. The company put the investment at $17 billion and contracted a 702 MW fuel cell project with American Electric Power, built by Bloom Energy. These are company commitments. Cheyenne Light's proposed Large Customer Transmission Cost Adjustment Mechanism would shift the cost of transmission expansion onto data center customers, but it remains a proposal.

An older woman and a young girl holding a yellow tote bag that says 'Hello Wyoming' in a pumpkin patch.
Image: blog.google (press material)

The Microsoft side follows a different structure. On November 24, Cheyenne Light submitted three facility expansion agreements to the Federal Energy Regulatory Commission, logged under docket ER27-634-000. Microsoft pays for distribution and transmission facilities through contribution in aid of construction payments, which are upfront customer payments rather than rate-based recovery. Coverage of the filing reports that the agreements are redacted and contain no energy price, volume or supply term. Cheyenne Light stated to FERC that it does not think the commission has authority over these retail arrangements, yet it submitted them as a precaution. Proposed transmission projects for these Microsoft sites cost about $686 million.

Local Footprint and Open Questions

The scale matters for a utility with about 46,000 retail electric customers. Cheyenne Light set a system peak record of 439 MW in July 2026, and its data center pipeline stands near 3 GW, including about 600 MW of Microsoft and Meta projects, with roughly 2.5 GW more in early talks. The peak figure covers the whole system, not data center load, but the pipeline is several times that peak. Black Hills projects that the Google deal will add about $150 million to its net income, starting around 2030.

Environmental costs are only partly settled. Google states that its Wyoming campus will be air-cooled to limit strain on local water, and that a large majority of emissions from the fuel cell project will be captured and stored underground. Carbon capture rates, emergency dispatch rules and resource adequacy counting are not yet public. The sources report no noise measurements or air-permit results for the 564 MW gas plant, so its effect on nearby residents cannot be measured from the material available.

The microgrid model also departs from the usual utility path. In the traditional approach, a regulated utility builds generation and recovers cost through tariffs. In Cheyenne, the utility collects a return on its plant along with a management fee. Reportedly, the utility expects its unlevered free cash flow through 2048 to be substantial, though that is a projection rather than booked income, and the figure depends on contract terms that are described only in summary.

What Follows

They do not establish that ratepayers are insulated from the cost, or that costs are shifted onto hyperscalers. The mid-2027 Wyoming tariff decision and the FERC docket will show how wires costs are divided. Until then, the Google pledge and the Microsoft contribution payments remain untested by regulators.

While we strive for accuracy and rigor, ByteVyte can make mistakes. Readers are advised to verify all information independently and conduct due diligence before making decisions based on this reporting. We accept no liability for errors, omissions, or decisions made in reliance on this content.

Sources

https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/wyoming-data-center/